Texas toll roads: the road can work while the investment fails

SH 288’s termination shows how entry price, contracts and payment priority shape the equity result.

Monochrome generative point study “Twin Veil,” a mathematical form rendered in black and white.

On October 8, 2024, Texas paid $1,731,730,721 to terminate the private concession for SH 288’s managed lanes. The state already owned the corridor. It was paying to end a package of future operating and toll-revenue rights. The proceeds repaid debt before any remainder reached shareholders.S1, S2, S3

That payment did different things for different investors. A lender could be repaid while a recent equity buyer lost money: Abertis received $642.4 million after paying about $1.53 billion for 56.76% of the company, and recorded a €775.9 million pre-tax loss. A good road is not a good investment at every entry price, under every termination clause.S4, S5

Method & limits

Financial inputs are dated July 11, 2026; later exhibits state their own source periods. Sources checked October 25, 2026: original 2007 SH 130 allocation/term clauses from the verified archive, USDOT restructuring/repayment records, FHWA’s 2015 model guide, and the 2001 franchising paper. Guidance and proposed alternative designs are not governing Texas rights. No new private accounts, exact current cap table, complete SH 288 closing or legal opinion is claimed. Exhibits and modeled returns use their original definitions. Governance and billing guidance in the NTTA addition were checked October 23, 2026; financial comparisons use their original periods and evidence cutoffs.

Seven rights behind the word “owner”

Consider the North Tarrant Express, a 13.3-mile managed-lane concession on I-820 and SH 121/183 in the Dallas–Fort Worth area. Asking “Who owns it?” produces seven answers.

1. Physical ownership. The State of Texas owns the highway and right-of-way. The concession company did not buy a strip of Texas real estate. It received contractual rights within a state highway corridor.

2. Statutory control. The Texas Transportation Commission and TxDOT retain public authority over the facility: enforcement of the concession, oversight of safety and standards, approval rights over specified actions, and the ability to exercise contractual remedies. A concession is broad, but it is not sovereignty.

3. Revenue rights. NTE Mobility Partners, LLC is entitled to the managed-lane toll economics through 2061, subject to operating costs, debt service, revenue sharing, contractual restrictions, and handback requirements. That right is the investable asset.

4. Equity ownership. As of Ferrovial’s May 2026 fact book, a Ferrovial/Cintra affiliate held 62.97% and a Meridiam affiliate held 37.03%. Those percentages refer to the concession business, not 62.97% and 37.03% shares of the highway itself.S6

5. Debt control. At December 2025, NTE reported about $1.60 billion of project debt. Its bond documents restrict distributions if debt-service coverage falls below stated thresholds. Creditors hold liens on project revenues and contractual protections that can outweigh shareholder votes during distress. They can restrict equity distributions without owning the roadway.S6

6. Operations. The project company is responsible for operating and maintaining the managed lanes. Toll billing is handled through the North Texas Tollway Authority’s collection platform; under the disclosed arrangement, TxDOT remits amounts to the concession project within two to three business days. That shifts much of the tag and collection risk away from the private operator even though traffic risk remains with the project.S6

7. Residual ownership. When the concession ends, the contractual toll and operating rights expire and the asset remains with the state, subject to the agreement’s handback condition. The private toll rights are finite; continuing those receipts after 2061 requires support for continuing rights. Any settlement, reserve release or other residual claim needs its own contractual basis.

Following the payment separates those rights. The state holds the pavement; lenders, shareholders and operators claim different parts of its earnings. The billing agent processes the driver’s payment, while the agreement determines who can keep it.

Value depends on enforceable rights to charge tolls, set rates, operate, access the corridor, and claim contractual protection—plus the time remaining before those rights expire.

From toll collections to equity cash

Figure 02From toll bill to residual cash
01
Billed tollstransactions × realized toll
02
Collection lossesdiscounts, exemptions, leakage, unpaid bills
03
Operating cashcollection, customer service, routine O&M
04
Lifecycle capitalpavement, structures, software, mandatory capacity
05
Financing claimsinterest, principal, reserves, covenant tests
06
Public sharerevenue sharing, taxes, transfers where applicable
07
Equity residualdistributable only after every senior claim
High EBITDA does not equal cash available to equity. Collection, maintenance, leverage, reserves, and public sharing sit between traffic and distributions.BasisSponsor disclosuresTxDOT project reporting

A toll-road model begins with:

Gross toll revenue = traffic volume × average toll paid

Define traffic consistently: transactions, trips, axles, and vehicle miles are different measures. Average tolls vary by trip, time, vehicle, occupancy, tag status, and congestion. Billed revenue also differs from collected cash.

The simplified cash waterfall is:

Billed tolls
  – HOV discounts, exemptions, leakage, and unpaid bills
  – collection and customer-service costs
= collected toll revenue
  – routine operations and maintenance
  – major maintenance and lifecycle capital spending
= cash available before financing
  – interest and scheduled principal
  – required debt-service and maintenance reserves
  – government revenue sharing
  – taxes, where applicable
= cash available for equity distributions

Each deduction has a different driver.

Traffic volume responds to population, employment, trip patterns, freight, fuel prices, remote work, and the quality of free alternatives. A growing metropolitan area can still produce weak toll demand if the corridor is in the wrong place, ramps do not match origins and destinations, or development arrives later than forecast.

Average toll reflects more than posted price. On a fixed schedule, it moves with trip length, vehicle mix, and periodic rate decisions. On a managed lane, software may reprice every few minutes to preserve speed. Drivers buy access and a higher probability of arriving on time.

Collection quality affects both cost and cash recovery. Electronic tags cost less to collect and are more likely to yield payment than mailed invoices. Administrative fees can improve recovery but create political resistance. The DFW concessions are unusual because NTTA handles billing and the project companies receive rapid public remittance. Their margins are not a benchmark for roads bearing their own violation and collection risk.

Operating costs may be modest in a mature electronic system, but pavement, bridges, software, gantries, drainage, and required lane additions create large, uneven capital obligations.

The North Tarrant Express illustrates the distinction. In 2025 it reported $323 million of revenue and $278 million of adjusted EBITDA, an 86.1% margin. LBJ Express reported $244 million and $202 million, an 82.8% margin. NTE 35W reported $368 million and $294 million, a 79.9% margin. Calculated revenue per transaction was about $8.73, $5.30, and $7.08, respectively. These sponsor-reported adjusted EBITDA figures benefit from the collection arrangement. Audited cash available for debt service is a different quantity.S6

Debt changes what those margins mean. Reported 2025 net debt was about 5.3 times adjusted EBITDA at NTE, 10.1 times at LBJ, and 5.6 times at NTE 35W. LBJ can therefore have a high operating margin and still be the most financially sensitive of the three. Interest, principal, reserve requirements, and refinancing terms sit between EBITDA and the shareholder.S6

Revenue sharing limits equity’s upside. The DFW agreements use progressive formulas that can transfer up to 75% of revenue above specified bands to TxDOT. During 2025, disclosed government-sharing amounts included $26.4 million at NTE 35W and $8.1 million at NTE, plus sharing of refinancing gains and the LBJ “Wishbone” extension. Strong performance does not flow one-for-one to equity.S6

Mature roads still require capital. NTE’s mandatory capacity improvement was triggered in 2023. The project disclosed roughly $355 million of works, financed partly with a $414 million private activity bond issue; construction was 67% complete at year-end 2025. An investor valuing the road on current EBITDA without the contractual expansion would overstate equity value.S6

Pricing power is conditional

The DFW managed lanes reprice as often as every five minutes. For 2026, the disclosed “soft cap” was $1.156 per mile, indexed to CPI-U. Rates can exceed it under mandatory congestion conditions, with the system designed around a 50 mph service target. Heavy vehicles face multipliers. Qualifying high-occupancy vehicles receive discounts that are reimbursed under public arrangements.S6

Contractual pricing power remains subject to demand:

Revenue = toll price × paid traffic

Higher rates increase revenue only when lost volume is small enough. Managed lanes may raise peak prices to preserve speed; off-peak increases can empty the road. Political tolerance can constrain rates even when contracts permit them.

SH 130 uses a different framework. Its concession ties annual toll escalation to nominal Texas gross state product per capita and does not require reductions when that measure falls. The former SH 288 contract combined dynamic pricing with annual parameters: a minimum increase equal to the greater of 2% or CPI, and a cap equal to the greater of 3% or nominal Texas GSP per capita. These clauses can provide inflation protection, but only if drivers continue to pay.S13, S4

A price-volume threshold makes the demand condition explicit. In an illustration, a 10% toll increase breaks even on gross revenue only if paid traffic is at least 1/1.10, or 90.9%, of its previous level. A 5% traffic decline raises revenue 4.5%; a 15% decline lowers it 6.5%. That holds mix and trip length fixed. Dynamic pricing can also change reliability, so the response is a corridor-and-time question rather than a universal elasticity.

Even the favorable revenue case is not an equal percentage increase in equity cash. Collection terms, government sharing, lifecycle work and financing tests still intervene. I would use the contractual waterfall with the new traffic/price case before crediting the residual owner with the full gross increase.

Leverage makes the equity behave like an option

Suppose a concession is worth 100 and carries 70 of debt. Equity is 30. A 10% decline in enterprise value reduces equity to 20, a 33% loss. A 20% increase raises equity to 50, a 67% gain. The road’s physical condition can be unchanged while the equity value moves sharply.

Greenfield projects must service debt before traffic matures. A miss in year three can exhaust liquidity even if demand improves by year fifteen. Public networks can spread ramp-up risk; a stand-alone concession may lack that capacity.

Concession life adds another constraint. A road with 35 years remaining is not equivalent to one with 70 years. Every year that passes removes a year of cash flow. A valuation can include a handback payment only if the contract provides one. It cannot append a perpetual terminal value to a right that legally expires.

Why institutions still want the exposure

Pension and infrastructure funds seek long duration, entry barriers, and indexed prices. Insurers and bond investors seek contractual debt service. Banks finance construction and refinancing; distressed funds buy impaired claims and may convert them into equity.

A seasoned corridor can remove much of the construction and traffic-ramp uncertainty while leaving a price-sensitive security. The buyer still inherits remaining capital works, debt, sharing and a finite term. A brownfield cash-flow record deserves a different valuation from a greenfield forecast; neither deserves a valuation independent of its contract.

Governments use concessions to add capacity and transfer risk. A private consortium can supply equity, construction execution, and balance-sheet capacity; it can accept cost, schedule, traffic, and lifecycle risks that a public agency does not want. The structure can advance a road earlier. SH 130’s federal project record says TxDOT estimated the P3 delivered Segments 5–6 about 20 years sooner than conventional funding would have allowed.S11

NTE and LBJ combined private equity with federal TIFIA loans, tax-advantaged bonds, and public funds. Private equity costs more than public tax-exempt debt. Acceleration, transferred risk, and operating incentives must justify that premium and the contract’s constraints.

2025 sponsor-reported snapshotUSD / adjusted figures
2025 sponsor-reported operating snapshot for DFW toll-road projects
ProjectRevenueAdj. EBITDAMarginNet debt / EBITDARevenue / transaction
North Tarrant Express$323M$278M86.1%5.3×$8.73
LBJ Express$244M$202M82.8%10.1×$5.30
NTE 35W$368M$294M79.9%5.6×$7.08

Scroll the table to compare every column.

These are Ferrovial-adjusted operating measures, not audited project cash available for debt service. The leverage ratio is the more revealing contrast: LBJ carries the tightest financial cushion.SourcesFerrovial Fact Book · May 2026

SH 130’s creditors inherited the failed equity story

Traffic fell short and the original equity was eliminated while the road continued to operate. The SH 130 bankruptcy study puts the original financing beside the reorganization and explains what creditors received. That is the case to use for the capital stack and its dates.

SH 288: termination changed the equity outcome

Case 02 / SH 288Public title + private rights + state termination
201652-year concession executed

Texas keeps the corridor; the project company receives toll and operating rights.

2023Abertis buys 56.76%

Approximately $1.53B for the controlling economic stake.

Oct. 8, 2024Texas pays $1,731,730,721

Debt is retired first; toll and operating control revert to the public structure.

2025 filingAbertis reports €775.9M loss

Creditors can be made whole while recently purchased equity loses heavily.

Texas did not repurchase its land. It paid to terminate the finite private bundle of toll, operating, and revenue rights.SourcesCommission payment recordAbertis acquisition2025 accounts

SH 288 followed a different path. Traffic and operating margins were strong enough to attract a major brownfield investor, but the government exercised an option that ended the private equity story.

TxDOT executed the comprehensive development agreement in March 2016 with Blueridge Transportation Group. The project added four managed lanes over 10.3 miles, rebuilt major interchange components, and placed operation and maintenance obligations on the concessionaire. Substantial completion occurred in November 2020. The contractual term ran to March 2068.S1, S3

The reported project cost was $1.0635 billion. Financing included $298.6 million of private activity bonds, a $357.0 million TIFIA loan, $14.9 million of capitalized TIFIA interest, $17.1 million of public funds for the Texas Medical Center connection, and $375.3 million of developer and third-party equity. Original participants included ACS Infrastructure, InfraRed, Shikun & Binui, Northleaf, Clal, and Star America.S3

By late 2023 the cap table had consolidated. Abertis acquired 56.76% for about $1.53 billion; ACS retained 43.24% through ACS SH288 Holdings, LLC. The acquisition presentation reported 2023 pro forma revenue of $90 million, adjusted EBITDA of $66 million, and gross debt of $654 million at December 31, 2022. The lanes used dynamic pricing, with contractual annual parameters tied to CPI and Texas nominal GSP per capita.S4

Section 31 gave the state a termination-for-convenience right. In July 2024 the Texas Transportation Commission determined that exercising the right was in TxDOT’s interest. The concession ended on October 8. Control reverted to TxDOT, and the Texas Transportation Finance Corporation was authorized to develop and operate the project. The state funded the $1.7317 billion payment through a State Highway Fund loan, later refinanced with roughly $1.7 billion of TTFC toll-revenue and refunding bonds.S1, S2, S22

The federal project record specifies the waterfall: termination proceeds first repaid all outstanding debt, including TIFIA, and the balance was available to shareholders. The TIFIA loan was repaid in full on the termination date. Abertis reported receiving $642.365 million and recording a €775.857 million pre-tax loss, or €581.892 million after tax.S3, S5

Each valuation comparison has limits.

Implied equity value at Abertis entry: $1.53 billion divided by 56.76% equals approximately $2.70 billion for 100% of the equity. Adding the separately reported $654 million of gross debt produces an indicative enterprise value of $3.35 billion. This mixes a late-2023 transaction price with debt measured at year-end 2022, so it is a rough inference, not a closing balance sheet. Termination payment multiples: $1.7317 billion equals 19.2 times 2023 pro forma revenue and 26.2 times adjusted EBITDA. Those are gross transaction multiples because the payment covered debt and equity; they are not equity multiples. Estimated gross equity pool: subtracting approximately $650 million of debt from the payment leaves about $1.08 billion before fees, reserves, hedges, working-capital adjustments, and other claims. The actual shareholder distributions need the closing statement. Value per remaining concession year: the payment divided by approximately 43.4 remaining years is $39.9 million per year. This descriptive ratio ignores when the cash arrives; early cash flow is worth more than late cash flow. Payment versus original equity: the state’s gross payment was about 4.6 times* the original $375.3 million equity contribution. That does not mean the original sponsors earned 4.6 times. Debt was repaid first, ownership changed, capital may have been added or distributed, and the money was invested over years.

Abertis’s loss is a result for a particular buyer, entry price and holding period. The lender’s recovery is a result for a different claim. Texas acquired the ability to redirect decades of service and revenue, while financing the purchase itself. Collapsing those outcomes into “the private sector won” or “the state bought the road” loses the transaction’s most useful information. The closing waterfall and each investor’s dated cash flows are the right units of comparison.

For fiscal 2025, TxDOT reported $107.35 million of SH 288 operating revenue, $11.36 million of operating expense, and $2.73 million of maintenance expense, excluding the later bond refinancing treatment. TxDOT has said public control should permit lower tolls and slower escalation than under the former concession. HCTRA supports billing and account functions; TTFC holds the public operating and revenue mandate.S21, S22

SH 288’s buyout cannot price NTE, LBJ, NTE 35W, or SH 130. Their termination language, toll rules, debt, remaining lives, and obligations differ. SH 130 also has a federal equity holder. Any comparison requires the relevant concession agreement and compensation provisions.

Comparing public and private delivery

Public financing can use tax-exempt debt, pooled network pledges and an indefinite public operating life. A mature system can carry a new link through its ramp-up. Those advantages can lower financing cost while also making a weak individual project harder to see inside a strong network.

Private equity can absorb cost, schedule or demand losses and give one counterparty responsibility for lifecycle work. The original SH 130 equity loss is a concrete reason to take that allocation seriously. The public side still has to identify what it retained: federal credit exposure, public contributions, compensation promises, collection support and the cost of monitoring a long contract.

The useful comparison holds the delivered road, opening date and lifecycle standard constant. It then values the differences in construction risk, maintenance incentives, demand exposure, financing and flexibility. A lower public borrowing rate cannot by itself price earlier delivery or a genuine transfer of overruns. A high private EBITDA margin cannot by itself establish that transfer occurred.

There is a strong case for private participation when public constraints would otherwise delay useful capacity and the contract places manageable risks with a party able to control them. There is a weaker case when the public supplies most protection while paying an equity premium for risks it has effectively kept. The answer requires the project’s continuing public obligations to be identified. An ownership label cannot supply that account.

The analogy to a bond, utility or property helps only partway. Location persists, while the concession’s cash right ends. Traffic remains a choice, and late-life maintenance can consume cash before handback. The investor owns the contract’s residual after those claims. The public is purchasing a service and a risk allocation that should be compared with its available alternative.

Trip demand determines corridor value

Texas has favorable population trends. The Census Bureau estimated 31.71 million residents on July 1, 2025, up 8.8% from the April 2020 base. Dallas–Fort Worth reached roughly 8.5 million, up about 11% over that period, with substantial growth in outer counties. Houston and DFW posted some of the country’s largest one-year metropolitan population gains in 2023–24.S23

The state’s activity centers are dispersed. Jobs, homes, airports, warehouses, ports, and industrial sites are separated by long road trips. Transit is limited for many suburb-to-suburb routes. Texas also carries substantial freight: the state freight plan reported roughly 4 billion tons in 2019 and projects more than 8 billion by 2050. Congestion data show that most of Texas’s worst bottlenecks remain concentrated in the four largest metropolitan areas.S24, S25

These conditions favor toll options but cannot rescue a badly placed road.

Value depends on trips: origins, destinations, bottlenecks, ramps, and minutes saved. A driver may pay $12 for reliability before a flight yet refuse $3 on a quiet weekend. Freight demand requires routes and toll costs that fit the shipper’s economics.

Free-road capacity is the clearest substitute. Widening a parallel highway can reduce toll demand, though construction disruption can temporarily increase it. Contractual protection against competing facilities is never absolute; governments preserve rights to improve their networks. SH 130’s agreement, for example, contained a competing-facilities zone but excluded I-35 and projects already in regional plans.S12

Remote work changes commute frequency and peak timing. Fuel prices increase bypass costs. Development generates traffic only after occupancy and road connections; freight growth helps only where vehicle rules and logistics routes fit.

The valuation-input matrix lists the ten questions behind the investment decision.

Analyst model / 2025-base screenFinite life / no terminal value
Scenario, not price.

These ranges are simplified DCF scenarios. They are not bids, carrying values, fairness opinions, or current security quotations.

Finite-life 2025-base valuation screening scenarios
ProjectBear EVBase EVBull EVBase equityBase discount rateInput status
North Tarrant Express$2.88B$4.44B$6.91B$2.84B7.25%DFW inputs source-backed
LBJ Express$1.89B$2.95B$4.50B$0.91B7.50%DFW inputs source-backed
NTE 35W$2.74B$4.72B$8.12B$3.12B7.75%DFW inputs source-backed
SH 130 Segments 5–6$0.56B$0.99B$2.12B$0.54B9.00%Revenue, EBITDA, and $450M debt estimated

Scroll the table to compare every column.

The model holds EBITDA margins constant and simplifies maintenance, sharing, cash tax, and handback reserves. It subtracts modeled debt from enterprise value rather than building a levered debt-service schedule; it omits refinancing, swaps, working capital, tax basis, and explicit growth capex. SH 130’s $81.7M revenue, $68M EBITDA, and $450M debt are analyst estimates. Scenario width—not the base case—is the main conclusion.DFW inputsFerrovial Fact Book

Which claims an investor can buy

Investment access, entry price, and the security’s rights matter as much as the corridor. A valuable road can offer no available equity or only a bond with limited upside.

The private concession table compares the contracts and capital structures of the five principal concessions.

NTE offers a seasoned corridor, strong reported cash flow, and about 35 years of term. Cumulative project distributions through 2025 were about $1.172 billion, 2.75 times original project equity before considering timing, additional capital, taxes, or residual value. The mandatory-capacity program and government sharing reduce free upside. A buyer would most plausibly enter through a sale by Meridiam, a sponsor-level transaction, or project bonds; Ferrovial’s listed shares provide diluted exposure across a much larger portfolio.S6

LBJ has an attractive urban bottleneck and 2025 adjusted EBITDA of $202 million, but its roughly 10.1 times net-debt-to-EBITDA ratio leaves less room for error. Cumulative distributions of $952 million exceeded original equity in nominal dollars, yet that statistic says little about today’s entry price. APG- or Meridiam-managed interests could theoretically trade in the secondary market. At the cutoff, no reviewed evidence showed them offered for sale.S6

NTE 35W produced the highest 2025 revenue of the three DFW concessions, $368 million, and has benefited from staged expansion. It also paid the largest disclosed 2025 revenue share. Its acquisition routes resemble LBJ’s: sponsor stakes, infrastructure-fund or pension secondaries, project bonds, or a recapitalization. The main valuation question is how much growth remains after sharing and future corridor obligations.S6

SH 130 is the more specialized opportunity. It has become a freight and reliability asset after a failed greenfield ramp-up. SVP’s continuation-vehicle process shows that institutional secondary capital can access it, but the exact 2026 debt, distributions, and cap table are not public. The U.S. government’s minority interest and any TxDOT transfer consent narrow the buyer universe. Upside comes from traffic, freight, adjacent development, and a possible extension; downside comes from repeating the original mistake by capitalizing those possibilities before they are contractual or realized.

SH 288 no longer offers concession equity. A financial investor can consider TTFC toll-revenue bonds, service contracts, or indirect exposure through firms operating for the state. These provide debt or service income. A bondholder receives contracted debt service. The residual toll upside that Abertis expected belongs to the equity claim.

Public systems mainly offer municipal debt with different pledges, tax support, coverage, and maturities. TIFIA is a federal lending program. Distressed exposure requires a purchasable project claim and enforceable restructuring rights.

A proven concession with 35 years left can disappoint at a 4% equity yield and become attractive after deleveraging. Public efficiency does not give bondholders residual upside. Assess the available security’s price against traffic, debt, maintenance, contractual, and political risks.

Public systems

Municipal bonds

Contractual debt service

Limited upside; pledge quality varies
Private concessions

Project bonds

Interest + principal

Traffic and covenant exposure
Sponsor or pension stake

Fund secondary

Equity distributions + exit

Transfer and government consents
Ferrovial shares

Listed sponsor

Diluted portfolio exposure

Texas is one part of a larger company
Project-specific loans/bonds

Distressed debt

Recovery or restructuring control

Rare, specialized, and document-heavy

Ownership determines payment priority

Texas’s toll-road examples support a more precise judgment than either ownership slogan. Public title protects the public asset; it does not identify every financial obligation the public has accepted. Private equity can bear a real loss; that loss does not erase federal lending or contractual compensation. The contract determines the division.

SH 130’s original investors lost their equity while the public road remained open. SH 288’s lenders were repaid while a recent shareholder suffered an entry-price loss. A future investor can buy only an available security with its actual claims, at its actual price. The existence of an attractive corridor creates neither access to that residual nor a guaranteed return.

I would begin any purchase or policy comparison by tracing the enforceable cash right and its ending, then testing traffic, lifecycle work, senior claims and the public obligations left around it. That is where a toll dollar becomes an investment return—or a public commitment somebody else must finance.

The road-by-road records

The ownership map and data appendix holds the road lookup, ownership tables and concession dates. The short ownership answer identifies the right question for a bill; this essay follows the investor’s rights after the owner is known.

Sources

  1. TxDOT, SH 288 Managed Lanes — executed agreements and termination page

    (primary; current through 2026). Establishes CDA execution, October 8, 2024 termination, reversion of control, and TTFC authorization.

  2. Texas Transportation Commission, July 30, 2024 minutes and July 31, 2025 minute orderAdditional source 2

    (primary). Establishes termination-for-convenience authority, the exact $1,731,730,721 payment, and State Highway Fund loan.

  3. U.S. DOT Build America Bureau, SH 288 project profile

    (primary federal financing record). Project cost, original financing, participants, completion, termination waterfall, and TIFIA repayment.

  4. Abertis, “Puerto Rico and SH288 acquisitions,” October 18, 2023

    (sponsor transaction presentation). Acquisition price and stake, pro forma revenue/EBITDA, gross debt, toll formula, and expiry.

  5. Abertis Infraestructuras annual accounts, 2025

    (audited company filing). SH 288 proceeds received and recorded loss.

  6. Ferrovial Fact Book, May 2026, filed with the SEC

    (current sponsor disclosure). DFW ownership percentages, concession terms, toll framework, 2025 operating figures, debt, distributions, sharing, and expansion.

  7. FHWA project profile, North Tarrant Express

    (primary federal project record). Original cost, financing, term, opening, and original partners.

  8. FHWA project profile, LBJ Express

    (primary federal project record). Original cost, financing, toll collection, term, and opening.

  9. FHWA project profile, NTE 35W

    (primary federal project record). Segment costs, financing, term, construction dates, and dynamic-pricing objective.

  10. TxDOT, SH 130 Segments 5–6 executed agreements

    (primary). Facility concession agreement and supporting documents.

  11. U.S. DOT Build America Bureau, SH 130 Segments 5–6 project profile

    (primary federal financing record). Cost, capital structure, concession, bankruptcy, and U.S. DOT debt and equity recovery.

  12. FHWA, Report on Highway Public-Private Partnership Concessions in the United States, 2016

    (federal analytical report). Original sponsor percentages, revenue-sharing and toll clauses, early forecast shortfall, liquidity stress, and bankruptcy context.

  13. Kentucky Public Pensions Authority, Project Spurs investment recommendation, September 6, 2024

    (public pension investment memorandum; sponsor-derived underlying data). SH 130 65/35 ownership, continuation vehicle, performance, toll escalation, concession term, and restructuring narrative.

  14. SH 130 Concession Company, current company history and FAQs

    (company source, updated through July 2026). State title, majority/minority ownership description, 2025 transactions, improvements, and current operations.

  15. NTTA 2025 Annual Comprehensive Financial Report

    (audited public-system statement). Traffic, revenue, debt, coverage, pledged system, and system assets.

  16. NTTA Board of Directors and system pages

    (primary governance source). Appointment structure and facilities.

  17. Harris County 2025 Annual Comprehensive Financial Report

    (audited county statement). HCTRA revenue, expenses, debt, coverage, cash flow, and transfers.

  18. CTRMA 2025 Annual Comprehensive Financial Report and governance page

    (audited authority statement). System composition, revenue, debt, coverage, and board appointments.

  19. Fort Bend County Toll Road Authority FY2025 Annual Financial Report

    (audited public authority statement). Revenue, debt, governance, and tax-supported obligations.

  20. Fort Bend Grand Parkway Toll Road Authority FY2025 Annual Financial Report

    (audited public authority statement). Right of use, revenue, debt, and county component-unit status.

  21. TxDOT HB 803 Report, FY2025

    (primary state project reporting). Revenue, operating expenses, maintenance, debt service, maturities, SH 288 transition, and non-financed facilities.

  22. TxDOT 2025 Popular Annual Financial Report

    (primary state financial summary). Toll-system net position and SH 288 funding/refunding context.

  23. U.S. Census Bureau, Texas QuickFacts and metropolitan population analyses, 2024–25Additional source 2Additional source 3

    (primary demographic data). State, DFW, Houston, Austin, and exurban growth.

  24. Texas A&M Transportation Institute, 2025 Texas’ 100 Most Congested Road Sections

    (research institute report using 2024 data). Congestion and truck-delay evidence.

  25. TxDOT Texas Freight Mobility Plan and port/freight statisticsAdditional source 2

    (primary state planning data). Freight tonnage, growth outlook, ports, and trade corridors.

  26. TxDOT NTE current executed-agreements indexVerified Oct 16, 2026

    Current source route; read the selected project’s agreement and amendments for actual terms.

  27. HCTRA FY2025 separate financial reportVerified Oct 16, 2026

    Authority-level audited financial report; fiscal year ended September 30, 2025. Supplemental source route, not a new reporting period.

  28. TxDOT — NTE 35W Amended and Restated Facility Agreement and Technical Provisions (official ZIP bundle)Verified Sep 23, 2026

    Access rechecked October 19, 2026. The agreement is available in TxDOT’s official ZIP bundle. The original contract analysis and its September 2026 evidence date are unchanged.

  29. FHWA — DBFOM toll-concession project profilesVerified Sep 23, 2026
  30. FHWA — Toll Facilities in the United StatesVerified Sep 23, 2026
  31. TxDOT — NTE project segments and developersVerified Oct 16, 2026

    Separately identifies developer for Segments 1/2W and Segment 3A/B/C I-35W project; no merger of project counterparties inferred.

  32. FHWA — public-private partnership agreement libraryVerified Sep 23, 2026
  33. NTTA — financial information and debt-obligation transparencyVerified Sep 23, 2026
  34. NTTA — September 2026 committee notice and authority descriptionVerified Sep 23, 2026
  35. HCTRA — FY2025 Toll Road Authority Enterprise Fund financial statementsVerified Sep 23, 2026
  36. NTTA — public authority, member counties and gubernatorial appointmentVerified Oct 16, 2026

    November2025 issuer release: institutional description and public appointment route. Does not reverify every project title or individual security.

  37. Texas Transportation Code, Chapter 366 — public status and board appointment powersVerified Oct 23, 2026

    Sections 366.032 and 366.251 establish governmental status and county/governor appointment powers. Checked for the dated governance addition; original financial claims retain their own sources and periods.

  38. NTTA — current facility, TEXpress operator and payment guideVerified Oct 23, 2026

    Separates NTTA facilities from TEXpress lanes; identifies private project and TxDOT operators; explains TollTag and ZipCash use. No private equity percentage or individual title search is inferred.

  39. TxDOT — TxTag accounts transferred to HCTRA and retained road responsibilitiesVerified Oct 23, 2026

    The Is TxTag going away FAQ says transferred customers may continue using the tag, directs account service to HCTRA and states that TxDOT retains road ownership, maintenance and rate-setting responsibilities. This is service guidance, not a title transfer.

  40. Least-Present-Value-of-Revenue Auctions and Highway FranchisingEngel, Fischer and Galetovic / Journal of Political Economy · 2001-10Verified Oct 25, 2026

    2001 model varies concession length with realized demand and a discounted-revenue target. Its assumptions and proposal do not describe the executed Texas fixed-term contracts or imply automatic extension.

  41. Model Toll Concessions Contract Guide, draft addendum, section 11Federal Highway Administration · 2015-01Verified Oct 25, 2026

    January 2015 guide explains lender cure, step-in, substitution, and bankruptcy-continuity provisions. It is a design reference, not a governing Texas agreement or a finding that a particular lender holds each right.

  42. SH 130 original Facility Concession Agreement, sections 2.2 and 4.2TxDOT / SH 130 Concession Company · 2007-03-22Verified Oct 25, 2026

    March 22, 2007 archived agreement. Selected clauses reread from the retained October 21 verified archive/OCR (PDFSHA2568 d 657 f 4573 f 0 cc 655189 d 9065243 a 953 da 4 ac 159453 a 8 b 4 d 1 bf 023 e 976 c 256 d 5). Distinguishes no general state debt liability from specific contractual/termination obligations; later amendments require separate review.