North Tarrant Express 35W

A separate project company and capital stack from NTE 1 & 2W.

Explore on map ↗

Ownership & control

01 / Public title & project rights

The asset and the business are different claims.

State of Texas / TxDOT public title; NTE Mobility Partners Segments 3 holds concession rights.

Scope of this record

I-35W Segments 3A, 3B and 3C. Staged works do not imply three independent concessions.

legal titleState of Texas / TxDOT

Public highway title retained by Texas

Snapshot 2026-10-22Executed facility agreement; project title and handback provisions ↗
concessionNTE Mobility Partners Segments 3, LLC

Finite concession and toll-revenue rights

Snapshot 2026-10-22Executed agreement and amendments; termination year separately sourced ↗
operatorNTE Mobility Partners Segments 3, LLC

Operation and maintenance under concession

Snapshot 2026-10-22Executed agreement ↗
public contract controlTexas Transportation Commission

Public agreement oversight; pricing and enforcement are contract-specific

Snapshot 2026-10-22CDA / facility agreement ↗
billingNorth Texas Tollway Authority

NTTA collection services; no transfer of concession ownership

Snapshot 2026-10-22Slide 41 ↗
equity interest · 53.67%Ferrovial / Cintra affiliate→ NTE Mobility Partners Segments 3, LLC

Reported project-company equity; affiliate-level chain not fully enumerated

Snapshot 2026-07-31Slide 32 ↗
equity interest · 28.84%APG-managed investor affiliates→ NTE Mobility Partners Segments 3, LLC

Reported project-company equity; affiliate-level chain not fully enumerated

Snapshot 2026-07-31Slide 32 ↗
equity interest · 17.49%Meridiam-managed investor affiliates→ NTE Mobility Partners Segments 3, LLC

Reported project-company equity; affiliate-level chain not fully enumerated

Snapshot 2026-07-31Slide 32 ↗
creditor claimBondholders (creditor class; individual holders unverified)→ NTE Mobility Partners Segments 3, LLC

Project financing claims; security holders not inventoried

Snapshot 2025-12-31Slides 43–45; amounts as of December 2025 ↗
lenderU.S. Department of Transportation / federal interest→ NTE Mobility Partners Segments 3, LLC

TIFIA creditor, distinct from equity

Snapshot 2025-12-31Slide 45 ↗

Financial record

Project bonds, TIFIA and facilities. Revenue sharing and financing restrictions constrain shareholder distributions.

Sponsor-reported project debt$1.6BPeriod ended 2025-12-31
Recorded financial observations · USD · scope: NTE Mobility Partners Segments 3, LLC
Metric / period endReported valueBasis & evidence
Sponsor-reported project debt2025-12-31$1,598,000,000sponsor-reported project debt, rounded USD millionsSlide 45 ↗

Public audited carrying values and rounded sponsor-reported project debt use different definitions. No statewide total, leverage ranking or return estimate is calculated.

Historical changes

The reported concession termination year is 2061. The Atlas records year precision; it does not invent a day or month.

Table 4, PDF p7 · termination year ↗

    No historical changes have been verified for this profile in this release.

    Evidence for this profile (3 records)
    1. TxDOT North Tarrant Express executed agreements ↗

      Separate Segments 1/2W and Segments 3A/3B/3C documents

      Reviewed 2026-10-22 · Primary source reviewed
    2. Ferrovial Fact Book 2026, July 31 amendment (SEC exhibit) ↗

      Slides 32 (equity and terms), 43–45 (financing). Sponsor disclosure, not a public-authority audit.

      Reviewed 2026-10-22 · Primary source reviewed
    3. TxDOT FY2025 HB 803 toll-project report ↗

      Reviewed 2026-10-22 · Original PDF retrieved and checked in this release

    Geography: Region anchor is an editorial locator. It is not a facility coordinate, alignment or asset boundary. Reviewed 2026-10-22. Source dates and financial periods are stated separately.